File #: 14-3634    Version: 1 Name:
Type: Report Status: Consent Calendar
File created: 12/19/2019 In control: City Council
On agenda: 1/7/2020 Final action:
Title: Contract Change Order No. 3 & No. 4 to R2Build dba R2B Engineering for Supplying Electrical Power to the Existing CNG Fueling Station Next to the Commerce Refuse-to-Energy Facility
Attachments: 1. Staff Report, 2. Resolution, 3. COR #001r Bollards, 4. COR #002rv Relocate Transformer Switchgear, 5. COR #003rv Retaining Wall, 6. COR #004 Relocate PB, 7. Clean Energy (R2Build Check), 8. Power to CNG Station Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Contract Change Order No. 3 & No. 4 to R2Build dba R2B Engineering for Supplying Electrical Power to the Existing CNG Fueling Station Next to the Commerce Refuse-to-Energy Facility

Recommendation

The City Council will consider for adoption a Resolution authorizing Contract Change Order No. 3 & No. 4 to R2Build dba R2B Engineering for Supplying Electrical Power to the Existing CNG Fueling Station next to the Commerce Refuse-to-Energy Facility.