Title
Approval of Professional Services Agreement for the Preparation of Plans, Specifications, and Engineer’s Estimate (PS&E) for a New Pocket Park Located on Gage Avenue and Zindell Avenue
Recommendation
The City Council will consider:
1. Approving a Professional Services Agreement (PSA) with the selected engineering consulting firm in the amount given in the fee schedule of the selected firm (ranges between $165,148 to $402,789) and authorize the Mayor to execute the agreement in a form approved by the City Attorney, and furthermore authorize City Manager and Public Works Director to execute any amendments to the agreement with the selected consultant should they become necessary; and
2. Approving up to 15% of the total contract value in contingencies for unforeseen additional design services; and
3. Approving up to 10% of the total contract value to provide project management services.
4. Adopt a Resolution appropriating between $206,500 to $503,500 from the Project Management Fund to support the design phase of the project.